TC Data Center Move
Scheduled Maintenance Report for Global Payments
Completed
The scheduled maintenance has been completed.
Posted Sep 17, 2022 - 06:00 MDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 17, 2022 - 03:00 MDT
Scheduled
TC Data Center move is scheduled for September 17, 2022

· TSYS is moving the Primary Center from Tempe to Suwanee on Saturday, September 17th for TC.

· When traffic is redirected during this event there will be a risk of client impacts. Merchants that connect to the platform via IP addresses instead of URLs will need to keep all IP addresses on their systems for inbound and outbound communications or monitoring.

· There will be intermittent processing issues during this event. Some in-flight authorizations will time-out during this event.
Posted Aug 30, 2022 - 15:46 MDT
This scheduled maintenance affected: Transaction Central (Hosted, Virtual Terminal, Recurring Billing, Batch Upload, Web Services, ACH Processing).